What Is Work Item Age?
Work item age is the time since a work item started, for items still in progress, in the Kanban Guide for Scrum Teams, and how that differs from cycle time.
By AIStackMatch Editorial · Updated · 9 min read
Some links on AIStackMatch are affiliate links. We may earn a commission if you purchase or sign up through them, at no additional cost to you. Read our affiliate disclosure.
Short answer
Work item age is the amount of time between when a work item started and the current time, and it applies only to items still in progress, in the January 2021 Kanban Guide for Scrum Teams. Cycle time needs a finish. The 2020 Scrum Guide does not define age. ClickUp's cards catalog does not name an age card.
Work item age is how long a piece of work has been in progress, counted up to now, while it is still open. The Kanban Guide for Scrum Teams, dated January 2021 and developed by Scrum.org with Daniel Vacanti and Yuval Yeret, defines it as the amount of time between when a work item started and the current time. The same sentence says this applies only to items that are still in progress. The Professional Scrum with Kanban glossary on Scrum.org uses that sentence for Age.
The November 2020 Scrum Guide does not define work item age. The Kanban Guide says it does not replace or discount any part of the Scrum Guide. It adds flow practices for a team that is already using Scrum. The time box those Sprints sit in is what is a sprint. The reason a given Sprint's work belongs together is the sprint goal. This page is the clock on items that have started and have not finished.
What is work item age?
The guide lists four basic flow metrics that Scrum Teams using Kanban need to track:
| Metric | The guide's definition | Still open? |
|---|---|---|
| Work in progress (WIP) | The number of work items started but not finished | The count of open items |
| Cycle time | The amount of elapsed time between when a work item starts and when a work item finishes | Needs a finish |
| Work item age | The amount of time between when a work item started and the current time. Only items still in progress | Yes |
| Throughput | The number of work items finished per unit of time | A count of finishes |
Start is not a status name the guide picks for you. It comes from the team's Definition of Workflow. Visualization has to include defined points at which the team considers work to have started and to have finished. There must be at least one active state. A work item, in the glossary, is a synonym of a Product Backlog item when Kanban is used within Scrum. The guide also says work items are the individual units of value flowing through the system, most likely as Product Backlog items. If the team counts bugs and chores as items, those items have an age once they pass the start point. No one outside the team should tell the team how to define that Workflow.
A task that started Monday and is still open on Friday has an age. It does not yet have a cycle time. The guide does not publish a formula such as "current date minus start date, plus one." That arithmetic is not in the January 2021 text. The unit of time is part of how the team reads the number. The guide's service level expectation example uses days. This page does not add a different unit.
Age stops being the right metric when the item finishes. Cycle time is then the elapsed time from the same kind of start to the finish. Throughput counts how many items finished in a period. It does not say how long the one still sitting in review has already been open. That is age.
How is age different from cycle time, a due date, and time in a status?
Cycle time is a record of something that ended. Age is a reading of something that has not. A team can have a short average cycle time and still have one item that has been open longer than that average. The average will not name it. The age will.
The guide's service level expectation (SLE) is the line the team compares that age with. An SLE forecasts how long an item should take to flow from start to finish inside the team's Workflow. It has two parts: a range of elapsed days, and a probability. The guide's example is that 85 percent of work items should be finished in eight days or less. That example is the guide's, not a target for your team. The SLE should be based on historical cycle time. If that history does not exist yet, the team makes its best guess and revises it once the history does. An item whose age is already past the range in the SLE has violated it. An item whose age is close, and which is still early in the workflow, is the one the guide tells the team to notice before the finish.
Little's Law, in the guide's prose, links WIP and cycle time: in general, for a given process with a given throughput, the more things you work on at any given time (on average), the longer it is going to take to finish those things (on average). The guide says that if cycle times are too long, the first action to consider is lowering WIP. Age is how you see that length while the item is still open, before the cycle time exists. The guide does not turn that paragraph into an equation, and this page does not add one.
A due date is a promise on a calendar. Age is time since the team's start point. An item can be young and already overdue, if someone set a due date before the work started. An item can be old and not yet due. The two clocks answer different questions. Time blocking is a way to reserve hours. It is not this metric.
Time in a single status is a third clock. It starts when the item enters that status, not when the team said the work started. A task that spent ten days in a backlog status and one day in review can show one day in the current status and a much larger age, if the team's start point was earlier. The definition of done is the finish the Increment has to meet. It is not an age.
Where does a Scrum team look at the number?
The guide does not add a meeting. It says the existing Scrum events are enough, and it names age in the Daily Scrum, not in a new ceremony.
The flow-based Daily Scrum keeps the goal the Scrum Guide already gives that event. The Kanban Guide says the meeting takes place around the board and focuses on where flow is lacking. The questions it adds include:
- Which work items are blocked, and what will unblock them?
- What is flowing slower than expected? What is the work item age of each item in progress? Which items have violated their SLE, or are about to, and what will get that work completed?
- Is anything off the board about to affect today?
- Did the team learn something that changes what it planned to do next?
- Is the WIP limit already broken, and what will let the team finish the work already in progress?
Age is in the second bullet, next to the SLE. Throughput is not in that bullet. Finished items have nothing left for age to say. The guide's Sprint Planning paragraph talks about historical throughput and capacity. The Sprint Review paragraph talks about flow metrics, progress toward the Product Goal, and throughput when the Product Owner discusses likely delivery dates. It does not repeat the age question there. The retrospective can use a cumulative flow diagram for WIP, an approximate average cycle time, and average throughput. Age is the metric you needed on the days before that diagram's finished items existed.
Active management is the practice that makes the number matter between events. The guide says limiting WIP is necessary and not sufficient. Inside the Sprint, the team also makes sure items are not left to age unnecessarily, and it responds to blocked or queued items and to items that are exceeding the expected cycle time. "Not left to age" is a policy. The chart, if you keep one, is how you notice.
The glossary names a WIP aging chart: a chart to visualize the age of active work items on the Scrum Team's workflow. The January 2021 guide does not specify the axes. This page does not invent them. A list of open items with a start date, sorted by that date, is enough to answer the Daily Scrum question. A chart is optional. The question is not.
Limiting WIP is what creates the pull system the guide describes. The team starts a new item when it has capacity, which the guide ties to the WIP limit. The team should stick to the limit once it is set. A standup that asks for age and then pulls three more items has skipped the practice the metric is there to support. How a 15-minute Daily Scrum can run is in how to run a standup.
What can you see in ClickUp without calling it age?
ClickUp Help's cards catalog does not name a card called work item age. Several cards measure time or due dates, and each one answers a different question:
| Question | What you can use | What it is not |
|---|---|---|
| How long has this item been in progress, from the team's start point, while it is still open? | No card with this name | |
| What is the average time from an Active status to Done or Closed, for tasks that have finished? | Cycle time card, on Business and above | It excludes tasks still in an Active status until they are closed |
| How long has the task sat in a status? | Time in status, on Business and above | The current status, not necessarily the workflow start |
| Which tasks are overdue? | Overdue Tasks, on Unlimited and above | A due date in the past, not age |
| Which tasks are due in the next 14 days? | Tasks Due Soon, on Unlimited and above | A due-date window, not age |
The cycle time gap is the one the Kanban Guide is describing. ClickUp cycle time averages a finished move. Help says tasks in an Active status are not included until they are closed. An item that has been active for twelve days and is not done does not appear on that average. Age is the name for those twelve days. ClickUp does not give you a card with that name. You can still see a start, if the team records one, by the status history or by time in status, and you should not relabel either number as the guide's age unless the start point matches the Definition of Workflow.
Time in status shows how long a task has been in a status. The List field shows the current status. Renaming a status resets that data. A reset column is not an age that survived a rename.
WIP limits color a Board column when the count is past the number you set, and the task can still move. That ClickApp starts on Business. The Kanban Guide tells the team to stick to the limit. A color that still accepts the card is a signal. The policy is still the team's.
Jira is the closer fit for a software team that already runs Scrum or Kanban on a board built for issues. Our data lists Scrum and Kanban boards and agile reports such as burndown and velocity. It does not list a work item age chart. ClickUp vs Jira is the comparison. ClickUp fits when the open work and the rest of the company's tasks should share one Workspace, and the team will compute age from a start point it defined. Trello is easier if a board is enough. Notion is stronger if the aging story is a written update. Asana is more polished if you want a lighter task product.
Ask for the age of each item in progress before you ask for a new item to start. The guide's order is the practice: see what is already aging, then decide whether the WIP limit still has room.
ClickUp
All-in-one work management for tasks, docs, goals and team collaboration, with a generous free plan.
Affiliate link. We may earn a commission at no extra cost to you. Read our affiliate disclosure
Frequently asked questions
What is work item age?
The Kanban Guide for Scrum Teams (January 2021) defines it as the amount of time between when a work item started and the current time. This applies only to items that are still in progress.
Does a finished item still have an age?
The guide limits age to items still in progress. Cycle time is the elapsed time from start to finish, and it needs that finish. The Professional Scrum with Kanban glossary uses the same age sentence.
Does the Scrum Guide define work item age?
The November 2020 Scrum Guide does not define it. The Kanban Guide says it does not replace the Scrum Guide. It adds flow metrics for a team that is already using Scrum.
Where does a Scrum team look at age?
The guide puts the question in the Daily Scrum: the age of each item in progress, and which items have violated or are about to violate the service level expectation.
Does ClickUp have a work item age card?
The cards catalog does not name one. The cycle time card excludes tasks that are still Active until they are closed. Time in status measures time in a status, which is a different clock.