Short answer

A sprint review inspects the outcome of the Sprint and decides future adaptations. The November 2020 Scrum Guide says the Scrum Team presents results to key stakeholders, discusses progress toward the Product Goal, and keeps the event a working session. For a one-month Sprint it is timeboxed to a maximum of four hours.

A sprint review is the working meeting near the end of a Sprint where the team and its stakeholders look at what the Sprint actually produced, and decide what that means for the next slice of work. The Scrum Guide, November 2020, published at scrumguides.org, states the purpose in one sentence: inspect the outcome of the Sprint and determine future adaptations. The Scrum Team presents the results of their work to key stakeholders, and progress toward the Product Goal is discussed.

The time box the review sits inside is a sprint. The longer objective they discuss is a product goal. The meeting that comes after this one, about how the team worked, is how to run a sprint retrospective. This page is the review. The ClickUp hub is the tool side, for teams that keep the work in ClickUp.

What is a sprint review?

The November 2020 section is three short paragraphs. It does not include a required slide order.

During the event, the Scrum Team and stakeholders review what was accomplished in the Sprint and what has changed in their environment. Based on that information, attendees collaborate on what to do next. The Product Backlog may also be adjusted to meet new opportunities. The Sprint Review is a working session, and the Scrum Team should avoid limiting it to a presentation.

That is the whole official agenda. "What was accomplished" and "what changed around us" are both in the sentence. A review that only plays a demo, and never asks whether the market, the customer, or the Product Goal still points the same way, has dropped half of the paragraph. A review that only talks about the market, and never inspects a result, has dropped the other half.

The Product Backlog may be adjusted. The Guide does not say it must be rewritten in the room, and it does not say the stakeholders reorder it. The Product Owner is accountable for the content and order of the Product Backlog. The Guide says those decisions are visible in the backlog and through the inspectable Increment at the Sprint Review. People who want a different order convince the Product Owner. They do not edit the list because they were invited.

A Scrum.org page titled "What is a Sprint Review?" quotes the 2020 purpose, then prints a longer list the review may include: what is Done and what is not, a demonstration, a discussion of dates, and a look at timeline, budget, and marketplace. That list is not in the November 2020 Sprint Review section. The 2020 section also does not forbid any of those topics. It simply does not require them. This guide does not add the longer list back in as rules. If your team uses a demonstration, it is because the result is easier to inspect that way, not because the 2020 section demands a demo script.

How long is a sprint review, and who is in the room?

The Sprint Review is the second to last event of the Sprint. It is timeboxed to a maximum of four hours for a one-month Sprint. For shorter Sprints, the event is usually shorter.

EventWhat the 2020 Guide says it is forMaximum for a one-month SprintWho the Guide names
Sprint ReviewInspect the Sprint outcome and determine future adaptationsFour hoursThe Scrum Team and key stakeholders
Sprint RetrospectivePlan ways to increase quality and effectivenessThree hoursThe Scrum Team. It concludes the Sprint
Daily ScrumInspect progress toward the Sprint Goal and adapt the Sprint BacklogFifteen minutes, any Sprint lengthThe Developers

The Guide does not publish a two-week review length. "Usually shorter" is the entire rule. A team that copies the four-hour ceiling onto a two-week Sprint is using a cap from a longer Sprint. A team that invents "the review must be 90 minutes" is adding a number the Guide does not contain. Stop when the outcome has been inspected and the next adaptations are clear. The timebox is a maximum.

"Key stakeholders" is the Guide's phrase for who is invited beyond the Scrum Team. It does not list job titles, and it does not say every interested manager attends. The Product Owner may represent the needs of many stakeholders in the Product Backlog. The review is where key stakeholders see the result, not where every stakeholder gets a standing seat. A room that cannot inspect the outcome because it is negotiating status has the wrong invitation list.

The Sprint Goal is not the subject line of this meeting. The Sprint Goal was the commitment for the Sprint that is ending, and the Developers keep it in mind while they work. The review discusses progress toward the Product Goal. What is a sprint goal is the single objective for one Sprint. You can meet the Sprint Goal and still learn, in the review, that the Product Goal should change. You can miss the Sprint Goal and still be pointed at the right Product Goal. They are different sentences, inspected in different conversations.

What can be presented at the sprint review?

The Increment rules are the part teams skip when they treat the review as a slide meeting.

An Increment is a concrete stepping stone toward the Product Goal. It is additive to all prior Increments, and it has to be usable. Multiple Increments may be created within a Sprint. The sum of the Increments is presented at the Sprint Review. An Increment may also be delivered to stakeholders before the Sprint ends. The Guide's line is direct: the Sprint Review should never be considered a gate to releasing value.

Work cannot be part of an Increment unless it meets the definition of done. If a Product Backlog item does not meet that definition, it cannot be released or even presented at the Sprint Review. It returns to the Product Backlog for future consideration. The moment an item meets the definition, an Increment is born.

SituationWhat the 2020 Guide says
The item meets the Definition of DoneIt is part of an Increment. The sum of Increments is presented at the review
The item does not meet the Definition of DoneIt is not presented at the review as done, and it is not released. It returns to the Product Backlog
The Increment is usable before the Sprint endsIt may be delivered then. The review is not a release gate
Stakeholders want a different backlog orderThey convince the Product Owner. The review makes the Increment inspectable. It does not transfer the Product Owner's accountability

Showing an unfinished item "so people can see progress" is the move the Guide rules out. Progress toward the Product Goal is discussed through results that meet the definition. A prototype that the team has agreed is not done can be mentioned as not done. It cannot be presented as the Increment.

The backlog is where the returned item goes. The review is allowed to adjust that backlog to meet new opportunities. An item that failed the definition is one reason to adjust it. A change in the environment is another. Both are in the Guide. Neither one requires a new meeting.

How is the review different from the retrospective?

The retrospective starts after the review and ends the Sprint. Its purpose is quality and effectiveness: individuals, interactions, processes, tools, and the Definition of Done. The review's purpose is the outcome and the next adaptations to the product. Stakeholders are named in the review. They are not named in the retrospective section.

The Daily Scrum is the 15-minute event for the Developers during the Sprint, aimed at the Sprint Goal and the next day's plan. A demo does not belong there. A process argument does not belong in the review if it is really about how the team worked. That argument has a meeting. It is the retrospective. How to run a standup is the short event. This page is the long one at the end.

A team using the January 2021 Kanban Guide for Scrum Teams still has this event. Flow metrics are a separate topic. A service level expectation is that guide's forecast of duration. It is not a Scrum commitment, and it is not a substitute for inspecting the Increment.

Where does this meeting live if you use ClickUp?

ClickUp Help does not document a Sprint Review event, view, or card. The cards catalog has no row with that name. ClickUp's sprint planning article describes planning, points, burndown, burnup, and velocity. At the end of a sprint it tells you to review incomplete tasks before closing. ClickUp prompts you to move them to the next sprint, send them back to the backlog, or close them. That prompt is a close-sprint choice. It is not the working session with stakeholders, and it does not know whether an item met your Definition of Done. ClickUp sprints is the ClickApp. The prompt belongs to that feature. The review belongs to the team.

A practical setup that does not pretend the tool is the event:

The Guide asks forA place it can liveWhat that place is not
Results that meet the Definition of DoneThe sprint List, with your real done status meaning the definitionA status named Done that the team has not agreed is the definition
Progress toward the Product GoalA Doc the team already treats as the goal, read out loud in the reviewA ClickUp Goal. Help does not name a Product Goal field
Notes on what changed and what to do nextA Doc next to the sprint, edited during the meeting, not after it from memoryThe close-sprint prompt
Items that are not doneBack on the backlog ListAutomatically the next sprint. The prompt offers that option. The Guide does not require it

Jira is the board many software teams already review from. It fits a group that lives in a dedicated issue tracker and wants the sprint reports in that tool. ClickUp fits when the sprint List, the Doc, and the stakeholders' shared view should be the same Workspace. The trade-off is the usual one: Jira is the tighter fit for a pure software team, and ClickUp is the tighter fit when the review includes people who will never live in an issue tracker. ClickUp vs Jira is the product comparison. Neither tool's help center, in the pages this guide relies on, schedules the four-hour timebox for you.

Hold the review before the retrospective. Show the sum of what is actually done. Put everything else back on the backlog in the open. Then close the sprint in the tool. The prompt is the bookkeeping. The review is the inspection.

ClickUp

All-in-one work management for tasks, docs, goals and team collaboration, with a generous free plan.

Affiliate link. We may earn a commission at no extra cost to you. Read our affiliate disclosure

Frequently asked questions

What is a sprint review?

The November 2020 Scrum Guide says its purpose is to inspect the outcome of the Sprint and determine future adaptations. The Scrum Team presents its results to key stakeholders, and progress toward the Product Goal is discussed.

How long is a sprint review?

A maximum of four hours for a one-month Sprint. For a shorter Sprint, the event is usually shorter. The Guide does not publish a separate number for a two-week Sprint.

Is a sprint review just a demo?

The Guide says it is a working session and that the team should avoid limiting it to a presentation. Attendees also review what changed in their environment and collaborate on what to do next. The Product Backlog may be adjusted.

What cannot be shown as done?

Work that does not meet the Definition of Done cannot be released or presented at the Sprint Review. It returns to the Product Backlog. The review is also not a gate that holds back an Increment that is already usable.

Does ClickUp have a Sprint Review event?

The cards catalog does not list a Sprint Review card. ClickUp's sprint planning article tells you to review incomplete tasks before closing a sprint, and prompts you to move, return, or close them. That prompt is not the Scrum event.