What Is an Increment in Scrum?
What an Increment is in the 2020 Scrum Guide, when one is born, and how that differs from a sprint review, a release, and a ClickUp status.
By AIStackMatch Editorial · Updated · 9 min read
Some links on AIStackMatch are affiliate links. We may earn a commission if you purchase or sign up through them, at no additional cost to you. Read our affiliate disclosure.
Short answer
An Increment is a concrete stepping stone toward the Product Goal. The November 2020 Scrum Guide says each Increment is additive to prior Increments, thoroughly verified, and usable. It is born the moment a Product Backlog item meets the Definition of Done. The Sprint Review presents the sum and is not a release gate.
An Increment is the usable result a Scrum Team adds to the product. The Scrum Guide, November 2020, published at scrumguides.org, defines it in the artifact section: a concrete stepping stone toward the Product Goal. Each Increment is additive to all prior Increments and thoroughly verified, ensuring that all Increments work together. In order to provide value, the Increment must be usable.
That is a product sentence, not a meeting sentence. The meeting that presents the sum of Increments is a sprint review. The quality bar that decides whether work may enter an Increment is a definition of done. The future state the stepping stone moves toward is a product goal. This page is the Increment. The time box around it is a sprint.
What is an Increment?
Three tests sit in the definition.
It is concrete. A slide that describes a feature is not a stepping stone. The Guide's word is a stepping stone toward the Product Goal, and the Product Goal is a future state of the product. The Increment is a piece of that product, in a condition the team can inspect.
It is additive, and it is thoroughly verified so that all Increments work together. A new slice that only runs if last month's slice is turned off has failed the "work together" line. Verification is part of the sentence. The Guide does not publish a test plan. It does say the Increment is verified, not merely described.
It must be usable, or it does not provide value. Usable is the Guide's word. A build that only the author can start, on a laptop nobody else has, is a poor match for that word. The Developers are the people committed to creating any aspect of a usable Increment each Sprint. The entire Scrum Team is accountable for creating a valuable, useful Increment every Sprint.
The Scrum definition at the top of the Guide puts the same idea in the sequence of the framework. A Product Owner orders the work. The Scrum Team turns a selection of that work into an Increment of value during a Sprint. The Increment is the output of the Sprint, not a status you apply at the end so the board looks finished.
When is an Increment born?
The commitment attached to the Increment is the Definition of Done. The Guide is direct about the moment: the moment a Product Backlog item meets the Definition of Done, an Increment is born.
Work cannot be considered part of an Increment unless it meets that definition. If a Product Backlog item does not meet it, it cannot be released or even presented at the Sprint Review. It returns to the Product Backlog for future consideration. The definition creates transparency: everyone shares an understanding of what was completed as part of the Increment.
| Situation | What the 2020 Guide says |
|---|---|
| The item meets the Definition of Done | An Increment is born. The work is part of the Increment |
| The item does not meet the definition | It is not part of an Increment. It is not released, and it is not presented at the Sprint Review. It returns to the Product Backlog |
| Several items meet the definition during the Sprint | Multiple Increments may exist. The review presents the sum |
| The Increment is usable before the Sprint ends | It may be delivered then. The review is not a gate |
| The organization already has a standard definition | Every Scrum Team follows it as a minimum |
| Several teams build one product | They mutually define and comply with the same Definition of Done |
If the definition is an organizational standard, all Scrum Teams follow it as a minimum. If it is not, the Scrum Team creates a definition appropriate for the product. The Developers are required to conform. Two teams and two definitions means their Increments are not comparable, and the Guide does not treat that as a local preference. One product, one bar.
The Guide does not publish a sample checklist. The checks depend on the product. What does not depend on the product is the rule: work that misses the bar is not in the Increment, even if the Sprint is ending and the review is on the calendar. What is a backlog is where that item goes back to.
Who decides how the Increment is built?
Sprint Planning is where the Increment gets a plan. The Developers plan the work necessary to create an Increment that meets the Definition of Done, often by decomposing Product Backlog items into smaller work items of one day or less. How this is done is at the sole discretion of the Developers. No one else tells them how to turn Product Backlog items into Increments of value.
The Sprint Backlog holds three things: the Sprint Goal (why), the Product Backlog items selected for the Sprint (what), and an actionable plan for delivering the Increment (how). The Sprint Goal is why this Sprint's work belongs together. It is not the Increment. You can meet a Sprint Goal and still have one item that missed the definition. That item is not absorbed into the Increment because the goal was met. It goes back to the Product Backlog.
The Product Owner's decisions show up in two places the Guide names together: the content and order of the Product Backlog, and the inspectable Increment at the Sprint Review. Stakeholders who want a different order convince the Product Owner. They do not edit the Increment by attending the review. The Increment is already the verified, usable result. The review makes it inspectable and discusses progress toward the Product Goal.
A Sprint could be cancelled if the Sprint Goal becomes obsolete. Only the Product Owner has the authority to cancel it. Cancellation does not rewrite the definition of an Increment that was already born. The Guide does not say a cancelled Sprint deletes usable work that met the Definition of Done.
How many Increments can a Sprint contain?
Multiple Increments may be created within a Sprint. The sum of the Increments is presented at the Sprint Review, which the Guide says supports empiricism. An Increment may also be delivered to stakeholders prior to the end of the Sprint. The Sprint Review should never be considered a gate to releasing value.
That paragraph is the one teams flatten into "we demo on Thursday and ship on Friday." The review presents the sum. It does not create the Increment, and it does not hold a finished Increment until the meeting is over. If the item met the definition on Tuesday and it is usable, Tuesday is an allowed delivery day. The review still happens. Its job is inspection and the next adaptations, including what changed in the environment, which is the review section. The Increment section's job is the result itself.
Empiricism, in the Guide's Sprint section, is the reason charts do not replace this. Various practices forecast progress, such as burn-downs, burn-ups, or cumulative flows. The Guide says they can be useful and do not replace empiricism. In complex environments, what will happen is unknown. Only what has already happened may be used for forward-looking decisions. An Increment is something that has already happened: verified, usable, additive. A forecast of remaining points is not an Increment. What is a burndown chart is that forecast. What is velocity is an optional indication of how much Product Backlog turned into an Increment. Velocity is not the Increment.
A release is also not the word the Guide uses as a synonym. The Guide talks about releasing value, and about work that cannot be released if it misses the definition. It does not say one Increment equals one version number, one app-store submission, or one customer's go-live. A team can deliver several Increments inside a Sprint and batch the public release. A team can deliver each Increment as it is born. Both fit the "not a gate" line. Neither fits if the thing being released missed the Definition of Done.
Where does an Increment live if you use ClickUp?
ClickUp Help does not document an Increment field, view, or card. A Done or Complete status is a property of a task. Sprint cards that count Done or Complete, including burnup and velocity, are counting that status. They do not read your Definition of Done. A task can sit in Done and still have missed a check the team wrote down. In that case the Guide says it is not part of the Increment, whatever the status is called.
A practical place for the agreement, without pretending the tool is the artifact:
| The Guide requires | A place it can live in ClickUp | What that place does not do |
|---|---|---|
| A shared Definition of Done | A Doc the team treats as the bar for the product | It does not mark tasks done by itself |
| The checks on one item | A checklist on the task | It is not a second, private definition |
| Work that met the bar | The sprint List, with a status the team only uses when the definition is met | The status name is not the definition |
| The sum you will inspect | The tasks that meet the bar, opened in the review | The close-sprint prompt, which moves, returns, or closes incomplete tasks |
| The Product Goal the Increment steps toward | A sentence the team already uses | A ClickUp Goal. Help does not name a Product Goal field |
ClickUp sprints is the sprint Folder, the points, and the close prompt. The prompt asks what to do with incomplete tasks. It does not know whether an item met the definition. Put items that missed the bar back on the backlog List in the open, then close the sprint. The Increment is the work you can already use.
Jira is the tracker many software teams already plan from, and it fits a group that wants sprint reports inside a dedicated issue tool. ClickUp fits when the sprint List, the Doc that holds the definition, and the people in the review should be the same Workspace. Jira is the tighter fit for a pure software team. ClickUp is the tighter fit when the Increment includes work from people who will not live in an issue tracker. ClickUp vs Jira is the product comparison. Neither tool's help center, in the pages this guide relies on, creates the Increment for you. The team does, when the item meets the definition and the result is usable together with what came before.
Call the result an Increment only when it is concrete, additive, verified with the rest, and usable. Keep everything else on the Product Backlog. Show the sum at the review. Ship earlier when the Increment is actually ready, and leave the status field as a label the team has agreed means the definition, not as a substitute for it.
ClickUp
All-in-one work management for tasks, docs, goals and team collaboration, with a generous free plan.
Affiliate link. We may earn a commission at no extra cost to you. Read our affiliate disclosure
Frequently asked questions
What is an Increment in Scrum?
The November 2020 Scrum Guide calls it a concrete stepping stone toward the Product Goal. Each Increment is additive to all prior Increments and thoroughly verified, so the Increments work together. To provide value, it must be usable.
When is an Increment born?
The moment a Product Backlog item meets the Definition of Done. Work that does not meet that definition is not part of an Increment. It cannot be released or presented at the Sprint Review. It returns to the Product Backlog.
Can a Sprint contain more than one Increment?
Yes. The Guide says multiple Increments may be created within a Sprint. The sum is presented at the Sprint Review. An Increment may also be delivered to stakeholders before the Sprint ends.
Is the Sprint Review a release gate?
No. The Guide says the Sprint Review should never be considered a gate to releasing value. The review inspects the outcome. Delivery can happen earlier, once the Increment is usable and meets the Definition of Done.
Does ClickUp have an Increment field?
Help does not name one. A Done or Complete status is a field on a task. The Increment is the usable result that meets the Definition of Done. A status name does not contain that agreement.