What Is a Burndown of Remaining Work?

What a burndown chart shows, how to read remaining work against an ideal line, and how ClickUp's Sprint Burndown card calculates it.

By AIStackMatch Editorial · Updated · 8 min read

Some links on AIStackMatch are affiliate links. We may earn a commission if you purchase or sign up through them, at no additional cost to you. Read our affiliate disclosure.

Short answer

A burndown chart plots work still left against time. The horizontal axis is time, and the vertical axis is remaining effort, often in points or hours. In ClickUp, the Sprint Burndown card is on Business and above, and the guideline appears only after you lock the sprint forecast.

A burndown chart is a picture of work still left. Scrum.org's glossary defines a burn-down chart as a chart of the amount of work thought to remain in a backlog. Time sits on the horizontal axis. Work remaining sits on the vertical axis. As items are finished, the line should fall. The glossary says the work can be counted in more than one way, including story points or task hours, and that either a sprint backlog or a product backlog can be the source.

The chart answers one question: at this pace, does the remaining work hit zero by the end of the time box? It does not say whether the work was the right work. That judgment belongs in the sprint review. The time box itself is in what is a sprint. How the work was sliced before anyone estimated it is in what is a work breakdown structure.

How do you read a burndown chart?

Two lines matter. One is the ideal, a straight drop from the starting commitment to zero on the last day. The other is actual work remaining. If the actual line stays near or under the ideal, the team is at or ahead of the pace the commitment implied. If it stays above, the remaining work is larger than that pace allows.

The lines move for reasons that are not "people worked slower." Adding scope pushes remaining work up. Re-estimating a task moves it. Finishing a task moves it down. A chart that only falls on the last day usually means status was updated late, not that the work appeared on Friday.

Here is the arithmetic on a made-up sprint, not a reported team. The commitment is 40 points over five working days. The ideal drops by 8 points a day, because 40 divided by 5 is 8. The remaining column is an illustration of a team that started on pace and then slipped.

DayIdeal remainingExample remaining
Start4040
Day 13234
Day 22430
Day 31628
Day 4818
Day 506

On day 5 this example still has 6 points left. The chart did its job if someone noticed the gap on day 2, when remaining was already 6 points above the ideal, and cut scope or asked for help then. A chart nobody looks at until the retrospective is a record, not a tool.

A burn-up chart is the companion, not a synonym. Scrum.org describes burn-up as work completed climbing toward a scope line. Burn-up makes added scope visible as a rising ceiling. Burn-down makes the gap to zero visible. Teams that keep adding work mid-sprint often read burn-up more honestly, because a burndown can look "fine" after someone quietly deletes tasks. ClickUp ships both as sprint cards. This page is the burndown.

A Gantt critical path is a third picture. It is the longest chain of dependent tasks on a calendar, not a count of effort left in a sprint. ClickUp documents that path on Gantt view. See ClickUp Gantt chart. Use the Gantt when the question is which task delays the end date. Use the burndown when the question is whether the sprint commitment is burning down.

How does ClickUp calculate a Sprint Burndown?

ClickUp's current Sprint Burndown card compares the work the team committed to finish in one sprint with the amount finished. Help says the vertical axis is the effort measure from Workspace or Sprint Folder settings: Sprint Points or time estimates. The horizontal axis is the current sprint by default. You can point it at the previous sprint or at a specific completed sprint in the same Sprint Folder.

The card includes tasks, subtasks, nested subtasks, and tasks or subtasks that also live in other Lists. Help says anyone who can view the chart sees the same data, regardless of their permissions on the related Folders and tasks. Do not put a burndown on a dashboard you share with a guest if that chart would reveal work they should not see. The permission on the chart is not the permission on each task.

Help names the numbers above and inside the chart:

FigureWhat Help says
ForecastedEstimated work for the sprint
Total effortWork in the sprint at a point in time, including scope changes and re-estimates. Shown as the net change divided by the forecast, as a positive or negative percentage
GuidelineA gray line for ideal progress, based on the tasks in the locked forecast. Forecast divided by the number of days. It does not calculate until you lock
Remaining effortThe locked total, which falls as work completes. New tasks added after the lock do not change it. Re-estimates or removals of tasks that were in the lock do
CompletedCumulative work set to a Done or Complete status, divided by the forecast
Completed dailyWork completed in each 24 hours

That split between total effort and remaining effort is the part people misread. Adding a task after you lock the forecast changes total effort, the scope percentage. It does not change remaining effort. Remaining effort still answers "what happened to the original commitment?" Total effort answers "how much did the sprint grow?" A late request that lands in the sprint is a scope change. The definition of that problem, separate from the chart, is in what is scope creep.

You must lock the forecast to mark the end of sprint planning. Help says this cannot be undone. Forecasted, guideline, and remaining effort all use the tasks that were in the sprint before the lock. For the current sprint, Help says the chart updates in real time, and you can refresh it from the icon at the upper right. Non-working days come from sprint settings and show with a gray background.

Hover the top of the chart and click Total effort, Completed, or Remaining effort to open drill-down. Help says you then see the sprint's tasks beside the chart, with status, assignee, priority, and the effort measure.

ClickUp still documents a legacy burndown card. On that older chart the vertical axis is a count of tasks, not points or hours. Help describes a blue line for work remaining, a yellow line for the current rate, and a red line for the ideal. Marking tasks Done or Closed shows up the next day. Adding tasks bends the line upward. Custom sprint durations do not work with legacy sprint cards. If the sprint length is custom, use the current Sprint Burndown card. The folder, the default two-week length, and the lock action are in ClickUp sprints. Points caps are in ClickUp sprint points.

Which plan includes the ClickUp burndown card?

Help's sprints limits page lists Sprint Cards as unavailable on Free Forever, Unlimited, and Core, and available on Business, Business Plus, and Enterprise. The cards catalog lists Sprint Burndown as an advanced card on Business and above, and unavailable below that. Sprints themselves, the Lists, are on every plan. You can run the time box without the chart.

Our prices, checked October 2026, list Free Forever at $0, Unlimited at $7 per user per month billed annually ($10 monthly), and Business at $12 annually ($19 monthly). Enterprise is custom. Our price data does not publish a Core or Business Plus price. Full notes are in ClickUp pricing.

Dashboards have a separate usage cap. The dashboards guide records Help's current row: 60 uses on Free Forever, 100 on Unlimited, and unlimited uses on Business and above. Uses do not reset. Those uses do not unlock the burndown card. A Free Forever Workspace can open a dashboard inside its cap and still have no Sprint Burndown. See ClickUp dashboards.

How do you add a Sprint Burndown card?

Help's steps:

  1. Create a dashboard or open one you already have.
  2. Click + Add card at the upper right.
  3. Select Sprints in the left sidebar.
  4. Click Sprint Burndown.
  5. Set the card, then click Add card.

The settings Help lists: one Sprint Folder as the source; a data source of current sprint, previous sprint, or a specific completed sprint; sprint length and non-working days, which come from sprint settings; and the effort measure, points or time estimates.

Help also says a Dashboard view is created automatically when a new sprint is created, and that the Sprint Reporting template includes a burndown among its cards. A different Help article says you cannot add a Sprint Burndown or Sprint Burnup card onto Sprint Folders, Sprint Subfolders, or Spaces. Use a dashboard, or the sprint's own dashboard view, rather than expecting the card picker on the Folder to offer it.

Jira is the alternative when the team is a software group that already lives in a dedicated tracker. Our data lists agile reports such as burndown and velocity on Jira. Jira is free for up to 10 users, and Standard starts at about $7.91 per user per month. Prices checked October 2026. ClickUp vs Jira and Jira pricing are the longer pages.

Lock the forecast when planning ends. Without that lock, ClickUp does not draw the guideline, and remaining effort has no baseline. Help says the lock cannot be undone.

Buy Business when you will actually look at the line during the sprint. Stay on Free Forever or Unlimited if the team only needs the sprint List and a board. A burndown you never open is a paid card. A burndown you check on day two, while there is still time to cut scope, is the reason the card exists.

ClickUp

All-in-one work management for tasks, docs, goals and team collaboration, with a generous free plan.

Affiliate link. We may earn a commission at no extra cost to you. Read our affiliate disclosure

Frequently asked questions

What is a burndown chart?

Scrum.org's glossary describes it as a chart of work thought to remain in a backlog. Time is on the horizontal axis and work remaining is on the vertical axis.

Which ClickUp plan has a sprint burndown?

Help's sprints limits page lists Sprint Cards, including burndown, on Business, Business Plus, and Enterprise. They are not on Free Forever, Unlimited, or Core.

Do you have to lock the forecast for a ClickUp burndown?

Help says you must lock the forecast for the guideline to calculate, and that locking cannot be undone. Remaining effort is based on the tasks in the sprint at lock.

Does adding a task after the lock change remaining effort?

Help says remaining effort does not change when tasks are added after the lock. It does change when tasks that were already in the forecast are re-estimated or removed. Total effort is the line that shows scope change.

Is a burndown the same as a Gantt critical path?

No. A burndown is remaining effort over a sprint. Critical path is the longest chain of dependent tasks on a schedule. ClickUp documents them as different features.