What Is Sprint Planning? Topics and the Timebox

What sprint planning is in the 2020 Scrum Guide, the three topics, the eight-hour cap, and how a ClickUp Sprint Folder holds the plan.

By AIStackMatch Editorial · Updated · 11 min read

Some links on AIStackMatch are affiliate links. We may earn a commission if you purchase or sign up through them, at no additional cost to you. Read our affiliate disclosure.

Short answer

Sprint planning is the event that starts a Sprint. The November 2020 Scrum Guide says the whole Scrum Team builds the plan, in three topics, in at most eight hours for a one-month Sprint. The output is the Sprint Backlog: the Sprint Goal, the selected items, and the plan to deliver them.

Sprint planning is the meeting that starts the Sprint. The Scrum Guide, November 2020, published at scrumguides.org, puts it in one sentence: Sprint Planning initiates the Sprint by laying out the work to be performed for the Sprint. The resulting plan is created by the collaborative work of the entire Scrum Team.

That is an event, not a folder and not a chart. The time box the event sits inside is a sprint. The objective the first topic has to finish is a sprint goal. The usable result the third topic plans toward is an Increment. This page is the planning event itself: who is in it, the three topics, how long it may run, and what you should have in hand when it ends.

What is sprint planning?

The Guide treats planning as the first formal chance to inspect and adapt inside the new Sprint. Events exist so the team inspects the artifacts on a regular cadence and needs fewer meetings that Scrum does not define. Skipping planning, or turning it into a status readout, drops that inspection. The Guide says failure to operate any event as prescribed results in lost opportunities to inspect and adapt.

The Product Owner makes sure attendees are prepared to discuss the most important Product Backlog items and how they map to the Product Goal. The Product Goal is the long-term target the backlog is there to meet. Planning is where that mapping is explicit for this Sprint, not where the Product Goal is rewritten. What is a product goal is that longer sentence. The Scrum Team may also invite other people to Sprint Planning to provide advice. The invitation is for advice. It does not move the accountabilities. The plan is still the Scrum Team's.

Three accountabilities show up, and the Guide does not merge them into one facilitator.

The Product Owner is accountable for the order of the Product Backlog and for what the product should become more valuable at. One person, not a committee. People who want a different order convince the Product Owner. Being in the room does not give them a second vote.

The Developers are accountable for creating a plan for the Sprint, the Sprint Backlog. They select the items, through discussion with the Product Owner. They also plan how the work gets done. The Guide's line is sharp: how this is done is at the sole discretion of the Developers. No one else tells them how to turn Product Backlog items into Increments of value.

The Scrum Master is accountable for the Scrum Team's effectiveness, including ensuring that all Scrum events take place and are positive, productive, and kept within the timebox. That is the eight-hour cap below. The Sprint Goal is still defined by the whole Scrum Team. The Scrum Master does not take the Developers' choice of how the work gets done.

What are the three topics?

The Guide splits the event into three topics. A planning meeting that only does the second one has produced a list, not a Sprint Backlog.

TopicThe Guide's questionWho actsWhat has to be true when you leave it
OneWhy is this Sprint valuable?The Product Owner proposes how the product could increase its value and utility. The whole Scrum Team defines the Sprint GoalThe Sprint Goal is finalized before Sprint Planning ends
TwoWhat can be Done this Sprint?The Developers select Product Backlog items, through discussion with the Product OwnerThe selected items fit what the Developers believe they can finish
ThreeHow will the chosen work get done?The Developers plan the work to create an Increment that meets the Definition of DoneOften a breakdown into work of one day or less. The method is the Developers'

Topic One is the value conversation. The Sprint Goal communicates why the Sprint is valuable to stakeholders. It must be finalized before the event ends, not in a follow-up after the Sprint has started. Scope inside the Sprint can still change later. The Developers collaborate with the Product Owner to negotiate the Sprint Backlog without affecting the Sprint Goal. That negotiation is a reason to finish the goal in the room. A goal written the next morning is not the commitment the Guide describes. The rest of that commitment is the sprint goal page. This page only needs the rule that planning is not over while the goal is still a draft.

Topic Two is selection. The Scrum Team may refine items during the event, which the Guide says increases understanding and confidence. Refinement is also an ongoing activity outside the event: breaking items down and adding detail such as a description, an order, and a size. Items that can be Done within one Sprint are deemed ready for selection. They usually reach that point through refinement, not through a speech in the first ten minutes of planning. The Developers who will do the work are responsible for the sizing. The Product Owner may influence them by helping them understand and select trade-offs. What is a backlog is the ordered list those items come from.

The forecast is the hard part of Topic Two, and the Guide names the inputs rather than a formula. Selecting how much can be completed may be challenging. The more the Developers know about their past performance, their upcoming capacity, and their definition of done, the more confident they will be in their Sprint forecasts. The November 2020 Guide does not use the word velocity. A velocity chart can inform "past performance." It is not a second rule that replaces those three inputs.

Topic Three is the plan for the Increment. For each selected item, the Developers plan the work necessary to create an Increment that meets the Definition of Done. The Guide says this is often done by decomposing items into smaller work items of one day or less. "Often" is the Guide's word. A one-day split is a common technique, not a rule that every task must be estimated at one day. What is a rule is who decides the split. A stakeholder who was invited for advice does not leave with the right to assign the subtasks.

The Sprint Goal, the selected items, and the plan for delivering them are together the Sprint Backlog. The artifact section says the same thing in a slightly different order: the Sprint Goal (why), the set of items selected for the Sprint (what), and an actionable plan for delivering the Increment (how). The Sprint Backlog is a plan by and for the Developers. It is updated throughout the Sprint as more is learned. It should have enough detail that they can inspect their progress in the Daily Scrum. Planning that ends with a goal and a pile of unreadable items has not finished Topic Three. The Daily Scrum, a 15-minute event for the Developers, is where that plan gets inspected on the following days. How to run a standup is that event. It is not a second planning meeting.

How long should sprint planning take?

Sprint Planning is timeboxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter.

The Guide does not publish a conversion such as two hours per week. A two-week Sprint is usually shorter than eight hours. It is not, on the Guide's page, automatically four hours. Teams that treat eight hours as the agenda for every Sprint, including a one-week Sprint, are using the cap for a one-month Sprint on a shorter one. Teams that book fifteen minutes and call it planning are also off the page: the event has three topics, and the goal has to be finalized inside it.

The other events make the size obvious. The Daily Scrum is 15 minutes. The Sprint Review is at most four hours for a one-month Sprint. The Sprint Retrospective is at most three hours for a one-month Sprint. Planning is the longest of the four. It is still a timebox, which means the work of the event fits in the box. It does not mean the team owes the calendar eight hours. The Scrum Master's accountability is to keep the event inside the box, and to keep it productive. Filling the box with a readout of last Sprint is the review's job, and the review has its own page: what is a sprint review.

Optimally, the Guide says, all events are held at the same time and place to reduce complexity. Planning can move. A moving planning meeting is a complexity the Guide tells you not to add without a reason.

A Sprint could be cancelled if the Sprint Goal becomes obsolete. Only the Product Owner has the authority to cancel it. Cancellation is not a planning outcome you schedule. It is what happens later if the goal the team just finalized no longer makes sense.

How does ClickUp hold a sprint plan?

ClickUp Help's sprint planning article uses the same name for a product setup. It defines sprint planning as selecting work items from a backlog and committing to complete them within a fixed period, usually one to four weeks. It also calls it a recurring meeting at the start of each sprint, where the team pulls from a prioritized backlog, agrees on what can realistically be finished, assigns tasks, and sets estimates. Those sentences are ClickUp's. The Scrum Guide does not say the meeting assigns tasks, and it does not set the Sprint at one to four weeks. The Guide's Sprint is one month or less. ClickUp's FAQ on that article adds that two weeks is the most common length and a good starting point, that one week suits fast feedback, and that three or four weeks suit complex features. That is the product article's advice. It is not a Scrum rule.

In the product, the backlog typically lives as a List inside a Sprint Folder, beside the active sprints. Help's planning steps, after that Folder exists, are short. Open the sprint, use the Backlog card, and click Add to sprint in the Sprints column. Several tasks can move through the Bulk Action toolbar. Then check Sprint Points. The article says the total points committed to the sprint become the forecast used for burndown and velocity. Then use the Assigned card to find unassigned tasks and distribute them. Workload view is the capacity check the article names: each person's assigned points or hours against their capacity. ClickUp sprints is the Folder, the duration, and the plan limits. Sprint points is the ClickApp.

Duration defaults to two weeks and can be set to any length at the Folder level. Only owners and admins configure those defaults. Members create sprints inside the settings. Point values are customizable. The article's common scale is 1, 2, 3, 5, 8, and 13, and it says you can set any values that fit the team. The same article's FAQ says a task worth 8 points is roughly twice as complex as a 4-point task, not twice as long. That ratio is ClickUp's FAQ. The Scrum Guide does not define points.

The article says three Dashboard cards are the clearest view once the sprint is running, all on the Business plan and above, added from the Sprints section: Sprint Burndown, Sprint Velocity, and Sprint Burnup. Velocity on that card compares committed points with completed points across three to ten sprints. The article tells you to use it during planning so the forecast comes from historical output. The catalog agrees those sprint cards start on Business. At the end of the sprint, ClickUp prompts you to move incomplete tasks to the next sprint, send them back to the backlog, or close them. That prompt is a close step. It is not Topic One, and it is not the Sprint Review.

ClickUp does not document an eight-hour timebox, a Sprint Planning card, or a check that the Sprint Goal was finalized before the meeting ended. The sprint goal guide covers the field ClickUp does document on the sprint. The meeting length is yours. The sprint duration setting is the length of the Sprint, not the length of the event.

NeedWhere it lives
Why this Sprint is valuable, finished before planning endsThe Sprint Goal, in the Scrum Guide. A field on the sprint in ClickUp
The items the Developers selectedThe Sprint Backlog. In ClickUp, tasks added from the backlog List
How the work will be doneThe Developers' plan, often items of a day or less. ClickUp subtasks if the team chooses that split
A forecast from past deliveryThe Guide's "past performance." ClickUp's Sprint Velocity card, on Business
The eight-hour cap for a one-month SprintThe Scrum Guide. Not a ClickUp setting

Jira is the closer fit when a software team already plans inside an issue tracker and wants that tracker to be the system of record. ClickUp vs Jira is the comparison. ClickUp fits when the sprint and the rest of the company's work should share one Workspace, and when a Sprint Folder next to ordinary Lists is enough structure. The ClickUp hub links the sprints feature, the points, and the charts. Trello is easier if the team wants a board and will not keep a Sprint Backlog. Asana is the more polished task product if you will not miss sprint cards.

Finish the Sprint Goal before the meeting ends. The Guide allows the selected work to change later, with the Product Owner, and it does not allow that change to replace the goal. ClickUp can store the tasks and the points. It does not keep the clock.

Run the three topics in order. Value, then the items that fit, then the plan for an Increment that meets the definition of done. Stop when those three are real, inside the timebox that matches the Sprint's length, rather than when the calendar hits eight hours. Put the result where the Daily Scrum can see it the next morning. In ClickUp that place is the sprint List, the points on the tasks, and, if you are on Business, the velocity card you will read at the next planning.

ClickUp

All-in-one work management for tasks, docs, goals and team collaboration, with a generous free plan.

Affiliate link. We may earn a commission at no extra cost to you. Read our affiliate disclosure

Frequently asked questions

What is sprint planning?

The November 2020 Scrum Guide says Sprint Planning initiates the Sprint by laying out the work to be performed. The whole Scrum Team creates that plan together.

How long is sprint planning?

The Guide timeboxes it to a maximum of eight hours for a one-month Sprint. For a shorter Sprint, the event is usually shorter. The Guide does not publish an hours-per-week formula.

What are the three topics of sprint planning?

Why this Sprint is valuable, what can be Done this Sprint, and how the chosen work will get done. The Sprint Goal must be finalized before the event ends.

What does sprint planning produce?

The Sprint Backlog. The Guide defines it as the Sprint Goal, the Product Backlog items selected for the Sprint, and the plan for delivering them.

Does ClickUp timebox the planning meeting to eight hours?

No. ClickUp's sprint planning article describes a meeting at the start of a sprint of usually one to four weeks, and a default sprint length of two weeks. It does not state the eight-hour cap.