ClickUp Sprint Task Report: What Changed After You Committed
How the ClickUp sprint task report, formerly the Action Report, splits committed, added, removed, completed, and remaining work for one sprint.
By AIStackMatch Editorial · Updated · 7 min read
Some links on AIStackMatch are affiliate links. We may earn a commission if you purchase or sign up through them, at no additional cost to you. Read our affiliate disclosure.
Short answer
The ClickUp sprint task report, formerly the Action Report, shows what a sprint committed to and what changed after that commitment: work added, removed, completed, and still remaining. It covers one sprint in one Sprint Folder. The card is on Business and above.
The ClickUp sprint task report answers a question a chart often blurs: what did you say you would do, and what did the sprint actually contain. ClickUp Help calls the card the Sprint Task Report, formerly the Action Report. It tracks tasks that were added, removed, re-estimated, and completed, and it is meant to show quickly what work was not completed. Help also says people know the same report as a say-do report, or an after action report: initial commitments compared with what was done in that sprint.
It is one sprint, not a trend. ClickUp sprint burnup is the line chart of scope against completed work for that same sprint. ClickUp cumulative flow is the stacked history of statuses. What is velocity is the average across several sprints. The task report is the list of changes inside one sprint. How the Sprint Folder is created is in ClickUp sprints. The ClickUp hub links those pages.
What do the sprint task report tiles mean?
Help says the report contains five tiles that break down tasks, committed effort, and remaining work, and that you can see when the sprint's scope gets bigger or smaller. A section called After Sprint Close sits beside those tiles. It populates after the sprint is done. If you mark the sprint done before the sprint has ended, Help says no changes are tracked in that section.
| Tile or section | What Help says |
|---|---|
| Committed | Sprint Points or time estimates on the tasks until the sprint is confirmed. This number does not change if more effort is added after confirming. Click the tile for the tasks, their status, when they were added, and the effort. Click a task to open it |
| Added | Increased scope from tasks added, or from effort re-estimated upward, after the sprint is confirmed. A task added after confirmation shows here, not on Committed. The Change column is zero when effort did not increase |
| Removed | Decreased scope from tasks removed, or from effort re-estimated downward, after confirmation. Click the tile for the tasks, when they were removed, and the decrease. The Change column is zero when effort did not decrease |
| Completed | Tasks completed after sprint confirmation and before the sprint is done |
| Remaining | Tasks that are not yet completed when the sprint is done |
| After Sprint Close | Populates after the sprint is done. Marking the sprint done early means this section does not track further changes |
Committed, Added, and Removed are written as effort. Completed and Remaining are written as tasks. Do not add those rows together as if they were the same unit. A sprint can show a small Added tile in points and a long Remaining list of tasks, if the unfinished tasks were estimated low.
The card accounts for all tasks, subtasks, and tasks and subtasks in multiple Lists in the selected sprint. The sprint-cards intro also says sprint cards include nested subtasks. The task report article itself names tasks, subtasks, and tasks in multiple Lists. Anyone with permission to view the chart sees the same data, regardless of their permissions on the related Folders and tasks. That is the same warning as on burnup: a guest who can open the dashboard can see the sprint's tasks on the chart, even when they cannot open every task. For the current sprint, Help says the chart data updates automatically. The daily 4:00 am note on the sprint-cards intro names Burndown, Burnup, Cumulative Flow, Lead time, and Cycle Time. It does not name this report.
How do you add a sprint task report?
Help's steps, for a dashboard or an Overview:
- From the upper right of an Overview, or of a new or existing dashboard, click + Add Card.
- In the left menu, select Sprints.
- Click Sprint Task Report.
- Configure the card.
- In the upper right, click Add card.
The choice on the card is which sprint to read. Help's data source options are the current sprint, the previous sprint (the last completed one), or a specific completed sprint in the selected Sprint Folder. You select one Sprint Folder. Sprint length, the effort measure, and non-working days are configured in sprint settings. Help also lists those three on the card, as the x-axis: length, non-working days, and Sprint Points or time estimates. Set them in sprint settings. Do not expect the report to invent a second effort measure for one sprint.
Dashboard views are created automatically for each sprint. You can turn that option off in sprint settings for the whole Workspace or for one Sprint Folder. The cards catalog lists Sprint Task Report on Dashboards and on Overviews, and not on Home. ClickUp dashboards is the canvas. The canvas cap and the Sprint Card plan gate are different limits.
You still need a confirmed sprint for the tiles to mean what Help says they mean. Committed stops at confirmation. Added and Removed start after it. Confirming, or locking the forecast on the burnup and velocity cards, is the line between the plan and the change log. ClickUp sprint points is the effort field if you are not using time estimates. Use one measure. A report that mixes "8 points added" with "6 hours removed" is not a scope change you can read.
Which plan includes the card?
| Plan | Sprint Cards | Sprint Task Report in the cards catalog |
|---|---|---|
| Free Forever | No | No |
| Unlimited | No | No |
| Core | No | No |
| Business | Yes | Yes |
| Business Plus | Yes | Yes |
| Enterprise and Max | Yes | Yes |
Sprints, the Lists, are on every plan. The report is not. Our prices, checked October 2026, list Free Forever at $0, Unlimited at $7 per user per month billed annually ($10 monthly), and Business at $12 annually ($19 monthly). Enterprise is custom. Our price data does not publish a Core, Business Plus, or Max price. Full notes are in ClickUp pricing.
Sprint Points include 100 uses on Free Forever and Unlimited. You can estimate inside that cap and still have no task report. Buy Business for the card, not for the time box.
A small example of the tiles
This table is an illustration of the definitions above. It is not a ClickUp export and not a published team result. The sprint was confirmed at 40 points. After that, someone added a 5-point task and removed a 3-point task. Eight tasks were confirmed. Six of those were completed before the sprint ended. Two were not.
| Tile | Example |
|---|---|
| Committed | 40 points. The 5-point add does not change this number |
| Added | 5 points, the task that arrived after confirmation |
| Removed | 3 points, the task taken out after confirmation |
| Completed | 6 tasks, finished after confirmation and before the sprint was done |
| Remaining | 2 tasks, not completed when the sprint was done |
The burnup for this example would show a ceiling that moved. The task report names the move: 5 in, 3 out, and 2 tasks still open. That is the say-do comparison Help describes. If the two remaining tasks missed a quality bar, the status still counts them as not completed. The quality bar is a definition of done, which this card does not read.
Jira is the closer fit when the team is a software group that already reviews scope inside a dedicated tracker. Our data lists agile reports such as burndown and velocity on Jira. Jira is free for up to 10 users, and Standard starts at about $7.91 per user per month. Prices checked October 2026. ClickUp vs Jira and Jira pricing are the longer pages. ClickUp fits when the sprint report should sit next to the client List and the Doc the rest of the company already uses.
Open the report at the end of the sprint, click Remaining, and write down why those tasks are still open. If Added is large every sprint, the planning meeting is the place to change the habit. The chart will not do that for you. It will keep the number visible.
ClickUp
All-in-one work management for tasks, docs, goals and team collaboration, with a generous free plan.
Affiliate link. We may earn a commission at no extra cost to you. Read our affiliate disclosure
Frequently asked questions
What is the ClickUp sprint task report?
Help calls it the Sprint Task Report, formerly the Action Report. It tracks tasks added, removed, re-estimated, and completed in one sprint, and what was not completed. It is also described as a say-do or after action report.
Which ClickUp plan includes the sprint task report?
The cards catalog lists Sprint Task Report on Business, Business Plus, and Enterprise and Max. It is not on Free Forever, Unlimited, or Core. Sprint Cards as a group use the same gate.
What are the five tiles on the report?
Help says the report contains five tiles: Committed, Added, Removed, Completed, and Remaining. After Sprint Close is a separate section that fills in after the sprint is done.
Does the committed number change when someone adds a task later?
No. Help says Committed is the points or time estimates on the tasks until the sprint is confirmed, and that number does not change if more effort is added after confirming. Later effort shows on Added.
How is the task report different from burnup?
Burnup is a chart of scope against completed work, with a guideline that needs a locked forecast. The task report is tiles for one sprint: what was committed, what was added or removed, what finished, and what remained.