ClickUp Task Duration: Schedule Work in Days

How ClickUp task duration sets a length in days, which plan includes it, and how elapsed days differ from a working-day duration.

By AIStackMatch Editorial · Updated · 6 min read

Some links on AIStackMatch are affiliate links. We may earn a commission if you purchase or sign up through them, at no additional cost to you. Read our affiliate disclosure.

Short answer

ClickUp task duration is a length in days, and the Duration ClickApp starts on Unlimited. Set any two of duration, start date, and due date, and ClickUp fills in the third. An elapsed duration counts weekends. A working-day duration skips them.

ClickUp task duration is how many days a task occupies on the calendar. It is not the hours you think the work will take, and it is not the timer. Help's rule is small: set any two of duration, start date, and due date, and ClickUp fills in the third. Move the start date later and a working-day duration keeps its length by pushing the due date.

The Duration ClickApp starts on Unlimited. Free Forever can still hold a start date and a due date. It will not calculate one from the other. The hours you plan to spend are ClickUp time estimates. The days the company treats as off are ClickUp work schedules. The product map is the ClickUp hub.

What is ClickUp task duration?

Help distinguishes two kinds of length.

A working-day duration skips non-working days from the Workspace work schedule. An elapsed duration counts every calendar day, including weekends and holidays.

Help's example uses a start date of May 1 and a duration of 10 days. With Skip Non-Working Days on, ClickUp sets the due date to May 14. With an elapsed duration, the due date is May 10. The example is Help's, so the gap is the weekends in that illustration, not a rule you have to memorize. Your Workspace workweek is what the skip actually follows.

You type the length in days. There is no hour field on this control. If the question is "this will take three hours," that is a time estimate. If the question is "this runs from Monday through Wednesday," that is a duration.

Which plans include task duration?

Help's scheduling table is the plan list. Pricing for automatic rescheduling can change, so read the live article if you are buying for this feature alone.

FeatureFree ForeverUnlimitedBusinessBusiness PlusEnterprise
DurationNoYesYesYesYes
Skip Non-Working DaysNoYesYesYesYes
Remap subtask due datesYesYesYesYesYes
Reschedule dependenciesYesYesYesYesYes
Parent and subtask date syncNoNoNoYesYes

Guests cannot enable ClickApps. Members cannot either. Admins can. Guests and members who have edit or full edit permission can set a duration on a task, and they can remap subtask due dates. The switch is the admin's. The value on the task is the editor's.

Prices checked October 2026: Free Forever is $0. Unlimited is $7 per user per month billed annually ($10 monthly). Business is $12 per user per month billed annually ($19 monthly). Our data does not publish a Business Plus price. Parent and subtask date sync is the row that needs Business Plus. Duration itself starts one plan earlier, on Unlimited. The published numbers are in ClickUp pricing.

How do you set a duration on a task?

Turn the ClickApp on before the field will calculate anything.

  1. Open the App Center.
  2. In the left sidebar, click Scheduling & Dates.
  3. Find the Duration ClickApp.
  4. Turn it on.

Then set it:

  1. Open the task.
  2. Click the Dates field.
  3. In the upper right of the modal, click the duration field.
  4. Type the length in days.

Elapsed length, the kind that includes weekends and holidays:

  1. Open Dates.
  2. Either set the due date to a Saturday or Sunday, or type e plus the length, for example e10d.

To convert a duration you already saved, click the Skip non-working days toggle in the duration field, or type a new length.

When the ClickApp is on, you can add Duration as a column, including on List view. When it is off, Help says members still see the Duration field, and they cannot add that field to views. If the column is missing, check the ClickApp before you rebuild the view. ClickUp List view is where that column usually sits. The same dates draw as bars on ClickUp Gantt chart.

Free Forever stores dates you type. It does not keep a duration when a date moves. If a slipped start date should push the due date by the same number of working days, that behavior starts on Unlimited.

How does duration work with dependencies?

Duration is one of three scheduling ClickApps Help tells you to turn on together: Duration, Skip Non-Working Days, and Reschedule Dependencies. The sequence in the scheduling article:

  1. Turn those ClickApps on.
  2. Create a List for the project.
  3. Add tasks for the main work and subtasks for the smaller pieces.
  4. Set a duration on each task and subtask.
  5. Set dependencies between all of them, with no gaps in the chain.
  6. Set the start date or the due date on the first task.

ClickUp then fills the remaining dates from the durations and the dependencies. When a date moves, dependent tasks move with it, and the duration on each task stays in force, skipping or including non-working days according to the setting you used.

Reschedule Dependencies is on every plan, including Free Forever. The duration those dependencies preserve is not. On Free Forever you can still link tasks, and you still type both dates yourself. ClickUp task dependencies covers waiting-on and blocking.

Two neighboring controls are easy to confuse with duration.

Remap subtask due dates is on every plan. When you move a parent due date later, ClickUp asks whether to move the subtask dates by the same amount or leave them. That pushes a parent change downward.

Parent and subtask date sync starts on Business Plus. It rolls the parent start to the earliest subtask start, the parent due date to the latest subtask due date, and the parent duration to the full span. That is bottom-up. Remap is top-down. Reschedule Dependencies moves tasks that are blocked, which is a third relationship.

Skip Non-Working Days uses the Workspace work schedule. The schedule itself, including the Monday to Friday default, is on every plan. Custom hours and holiday calendars start on Business Plus. The skip ClickApp starts on Unlimited, same as duration. Help's May 1 example only lands on May 14 when that skip is on.

Can a template keep task durations?

Yes, once the Duration ClickApp is on. Help says a template created before you enabled duration has to be updated before those lengths are included. The recommendation in that article is to leave start and due dates off the template and keep the durations. When you apply it, you set a start or a due date on the new tasks, and the duration schedules the rest.

To save durations, include everything, which brings durations along, or use Customize import items and leave Duration checked. To leave durations out, customize the import items and uncheck Duration. A List template that has dependencies, durations, and no dates can be applied with Import as-is. You then set the start or due date on the first task in the chain.

If the template already has dates, Help's remap option shifts them using the duration. One example in that article: a task that starts April 7, lasts 10 days, and is due April 18 lands on a new List as April 14, still 10 days, due April 25. If you choose Skip weekends while applying the template, elapsed durations convert to lengths that skip Saturday and Sunday.

Templates as a whole, including task templates that are not about dates, are in ClickUp templates.

Use duration when the calendar length should survive a date change. Use a time estimate when you need hours. Use both when a three-day review window still contains only four hours of actual work. Track the hours that were spent with ClickUp time tracking, which answers a third question and does not set the due date.

ClickUp

All-in-one work management for tasks, docs, goals and team collaboration, with a generous free plan.

Affiliate link. We may earn a commission at no extra cost to you. Read our affiliate disclosure

Frequently asked questions

What is task duration in ClickUp?

It is the number of days a task spans. Set any two of duration, start date, and due date, and ClickUp sets the third. You enter it in days, not hours.

Which ClickUp plan has task duration?

Help puts the Duration ClickApp on Unlimited, Business, Business Plus, and Enterprise. It is not on Free Forever. Skip Non-Working Days starts on Unlimited as well.

How do you set an elapsed duration?

Open Dates and either set the due date on a Saturday or Sunday, or type e and the length in the duration field, such as e10d. Elapsed duration counts weekends and holidays.

Is duration the same as a time estimate?

No. Duration is calendar length in days. A time estimate is effort, such as 1h or 30 mins, and that ClickApp is on every plan.

Can guests set a task duration?

Help says guests and members with edit permission can set a duration. They cannot turn the ClickApp on. An admin enables ClickApps.